That the Council notes the two options for an amended program for delivery of
the Springwood Town Centre Project outlined in this report, and resolves that
the dates included in the part resolution of Minute No 572 on 15 December 2009
are amended in accordance with Option A as follows:
This report presents options to amend the program for delivery of the
Springwood Town Centre Project. The program reported on 15 December 2009 was
delayed in commencement due to the rescission motion on this resolution and it
is now no longer possible to deliver the necessary information to the meetings
as resolved. The Council also stated a desire to debate the timing of conducting
a community opinion poll on the project. The two main options for timing of the
poll which have been identified are prior to Stage 2 of the tender process being
the Request for Detailed Proposals, or midway through the tender process after
the assessment of Part 1 of the Request for Detailed Proposals.
The Council resolved on 15 December 2009 to proceed with the Springwood Town
Centre Project as follows:
(Minute No. 572)
At the Council meeting of 15 December 2009 there was a debate among the
Councillors around the preferred stage within the program to conduct the
proposed community opinion poll. It was agreed that this debate would continue
in February 2010, in accordance with the resolution. The program informing this
resolution has now been reviewed and consequently shows options for timing of
the poll; allows for the delays over the holiday period, and in Option A (poll
on preferred proposal from tender after RDP Part 1 assessed) provides an
additional 4 weeks to the period to seek Request for Detailed Proposals (in
keeping with industry standards).
A summary of the revised program options is presented in Tables 1 and 2
below.
Option A proceeds to a community opinion poll midway in Stage 2 of the tender
after the Request for Detailed Proposals Part 1 has been assessed. The poll
would be on the delivery options for upgrading community and cultural facilities
and include specific details on the outcomes available through the preferred
proposal/s.
Option B undertakes a community opinion poll prior to proceeding to Stage 2
of the tender process. The poll would be on the general delivery options for
upgrading community and cultural facilities.
Dates for meetings have yet to be set as it is expected that the Council will
require these to be held in Springwood.
|
Matters for consideration
|
Method of consultation /
delivery
|
Time frame
|
Report to the Council
|
|
1.
|
Provision of information on the needs for community and
cultural facilities in Springwood and release of consultant
report
|
Consultant Report from October 2009 placed on the Council
website and in libraries, followed by other information as it
becomes available
|
January and ongoing
|
|
|
2.
|
Report amended program to the Council and seek amended time
lines for current Council resolution
|
EMT [Executive Management Team] considers program options
Email to Councillors in January
|
January
|
Report 2 February
|
|
3.
|
Council considers timing for consulting with the community by
way of poll on the process and outcomes of the Project: Design
process for representative survey of community opinion on
priorities (2 stages including initial survey on priorities for
provision in April and poll on proposed outcomes of preferred
proposal/s in November 2010)
|
Expert advice sought on options for polling before and after
commencement of stage 2 of the tender process (RDP Part1) with
independent consultant to design and conduct survey and to
design and supervise broader consultation processes
Councillor input and subsequent briefing.
Council debate at Council meeting
|
February - March
|
Councillor briefings 16 February and 23 March
Council report early April
|
|
4.
|
Documentation of requirements for community and cultural
facilities and other requirements for the development of each
site (including feasibility and costs).
|
Consultant engaged to prepare report
Stakeholder and Councillor input sought
|
Late January to mid March
|
Councillor Briefing 23 March
Report early April
|
|
5.
|
Conduct community consultation on priorities for community
facility improvements to inform way forward.
|
To be established within 4 (above). Likely to include phone
survey of a representative sample, complemented by a paper and
online survey / blog page on Council website.
|
April
|
Councillor Briefing 4 May (Katoomba)
Report late May in Springwood
|
|
6.
|
Prepare documentation for Request for Detailed Proposals
(RDP) - Stage 1.
|
External consultants to provide expert advice in preparation
of tender documents and probity plan.
|
April / May
|
Councillor Briefing on tender process and documentation 1
June
Confidential Report 8 June
|
|
7.
|
Seek Requests for Detailed Proposals (RDP) Part 1 - input
from internal advisers (Major Projects) indicates industry
standard of 10 to 12 weeks to respond to such calls.
|
3 proponents invited to formally submit RDP Part 1.
|
June / August
|
Confidential tender process
|
|
8
|
Tender panel assessment of RDP: Part 1: confidential process.
|
Tender panel composition and evaluation process managed in
accordance with Council policy and NSW Government guidelines.
|
September
|
Councillor Briefing 5 October (Springwood)
Confidential Report 12 October
|
|
9
|
Review design of community opinion poll process.
|
Independent consultant to design and conduct process.
|
Initial design prepared in February/ March for April 5
meeting and process reviewed September.
|
Councillor briefing on poll process and question: 5 October
Report 12 October
|
|
10
|
Conduct community consultation on proposed outcomes of
preferred proposal/s from RDP Part 1
|
Information provided to community on proposed outcomes of the
preferred proposal/s;
Community opinion poll on proposal/s conducted after
information has been made available
|
October / November
|
Councillor briefing on results of consultation 30 November
Report 14 December
|
|
11
|
Decision to invite proponent/s to proceed to RDP Part 2 of
tender process depending upon outcomes of the poll and on
Council and community satisfaction with one or more of the
detailed proposals.
|
|
12.
|
Seek RDP Part 2
|
Preferred proposal/s selected to continue.
|
March to May 2011
|
Council report July 2011.
|
|
Matters for consideration
|
Method of consultation /
delivery
|
Time frame
|
Report to the Council |
|
1.
|
Provision of information on the needs for community and
cultural facilities in Springwood and release of consultant
report
|
Consultant Report from October 2009 placed on the Council
website and in libraries, followed by other information as it
becomes available
|
January and ongoing
|
|
|
2.
|
Report amended program to the Council and seek amended time
lines for current Council resolution
|
EMT consider program
Email to Councillors in January
|
January
|
Report 2
February
|
|
3.
|
Council debate on timing for consulting with the community by
way of poll on the process and outcomes of Springwood Project:
|
Consultant advice prepared on options for polling before and
after commencement of Stage 2 of the tender process. Independent
consultant to design conduct community consultation and poll
process and broader community consultation processes; with
separate proposal to conduct and report on consultation
processes
Councillor input and then briefing.
Council debate at Council meeting 6 April
|
|
Councillor briefings 16 February and 23 March
Council report early April
|
|
4.
|
Documentation of requirements for community and cultural
facilities and other requirements for the development of each
site (including feasibility and costs).
|
Consultant engaged to prepare report
Stakeholder and Councillor input sought
|
Late January to mid March
|
Councillor Briefing 23 March
Report early April
|
|
5.
|
Information provided to community on delivery options and
proposed outcomes for community and cultural facilities and
broad commercial/ retail options;
Community poll conducted.
|
Independent consultant conducts poll process and provides
report on outcomes.
provides report on outcomes |
April / May / June
|
Councillor briefing on results of consultation 15 June
Report 29
June 2011
|
|
6.
|
Next steps will be depending on outcomes of community poll
and Council decision on way forward.
|
There has been no change to the financial matters as reported on 15 December
2009. Cost estimates to proceed with the project will be reported on 6 April
2010.
There has been no change to the legal and risk matters reported on 15
December 2009.
No external consultation has been undertaken since the report of 15 December
2009.
Two options for amending the program for delivery of the Springwood Town
Centre Project are presented for the consideration of the Council. The key
differences between Options A and B is the timing of a community opinion poll on
the delivery routes for upgrading of public facilities. Changes are recommended
to the dates in part resolution Minute No. 572 of15 December 2009 in accordance
with the program outlined in Table 1 of this report (Option A).